Difference between revisions of "Dynamic Load Management EVC16"

From Wiki
Line 40: Line 40:
 
1- By default, it is set to 3 seconds. However, there may be cases where the user needs to increase this value. For instance, if there are significant distances between the chargers and the ct clamps or if there are numerous interconnected chargers.
 
1- By default, it is set to 3 seconds. However, there may be cases where the user needs to increase this value. For instance, if there are significant distances between the chargers and the ct clamps or if there are numerous interconnected chargers.
 
# '''Measuring device''': The meter should be selected. For UK chargers, it is possible to choose CT clamps
 
# '''Measuring device''': The meter should be selected. For UK chargers, it is possible to choose CT clamps
# '''Energy meter address''': This information can be found in the meter settings accessed through the meter display. If the address cannot be located, it is recommended to consult the smart meter manual.
+
# '''Energy meter address''': This information can be found in the meter settings accessed through the meter display.  
 
+
# If the address cannot be located, it is recommended to consult the smart meter manual.
 +
[[File:Calibrate-ct.jpg|right|frameless]]
 
Note: Before calibration, CT have to be connected to the port, but not clamped around the cable.
 
Note: Before calibration, CT have to be connected to the port, but not clamped around the cable.
  
 
=== How to calibrate CT: ===
 
=== How to calibrate CT: ===
 
 
  
 
1- Before calibration, CT have to be connected to the port, but not clamped around the cable.
 
1- Before calibration, CT have to be connected to the port, but not clamped around the cable.
  
 
2- Check DLB CT and press Calibrate.  
 
2- Check DLB CT and press Calibrate.  
[[File:Calibrate-ct.jpg|right|frameless|304x304px]]
+
 
 
3 - Success.
 
3 - Success.

Revision as of 08:27, 28 February 2024

Pages with broken file links > Dynamic Load Management EVC16

Dynamic Load Management

Dynamic load management is a sophisticated feature that empowers users to efficiently control electric load by managing a group of chargers installed within a single circuit. Through the implementation of modbus RS-485 communication, the chargers are able to communicate with one another and dynamically adjust their charging power in response to the load on the grid, ensuring optimal charging operations and grid stability.

DLM Types

Dynamic load management (DLM) is a versatile solution applicable in various scenarios, providing users with the flexibility to choose between using it with or without ct clamps. Here are the key distinctions:

DLM with Ct Clamps:

This configuration is advantageous in the UK, where the use of CT clamps is beneficial for managing the electric load between chargers and other electronic devices. CT clamps enable precise control and optimization of the overall load, contributing to compliance with UK regulations. Their integration into DLM systems assists in efficient energy distribution, which is important for adhering to the energy standards and operational requirements suggested by UK energy authorities.

Ct clamps.jpg

CT Connection

Dynamic Load Management (DLM) is achieved through a carefully interconnected system of chargers, where communication is governed by a designated "Master" charger, dictating instructions to the remaining "Slave" chargers. These chargers can be interconnected either in a serial or parallel manner, each requiring the use of UTP twisted pair cables for communication via the A and B pins.


Ct-meter.png

DLM with smart meter:

This configuration enables users to efficiently manage the electric load between chargers and other electronic devices. By leveraging the capabilities of a smart meter, precise control and optimization of the overall load can be achieved.

DLM with meter.png


DLM without external measuring system:

In cases where the focus is solely on managing the electricity load between chargers and there are no additional electronic devices contributing to the load, this option can be utilized. It offers a simplified approach to load management, tailored specifically to charger interactions.


DLM without meter.png

Teltonika Energy App Settings

Once the chargers are properly connected to the electrical grid and interconnected to each other, the next step is to configure the settings for each charger using the Teltonika Energy app. Below, you will find a comprehensive list of the settings that should be adjusted to achieve DLM functionality.

Max power from grid

It is very important to set this parameter correctly in the master charger if you want to use DLM. This parameter shows how much of current you have in the circuit you want to balance. That means you have to set as much as this current can have amperes. Usually it should be the same current as the breaker tripping current. If for example in the master charger you will set lower current, DLM might not work and charger might not even start charging process.

For the slave charger, this parameter is not as critical. It is advisable to set it to a maximum of 16 A (for 11 kW chargers) or 32 A (for 7.4/22 kW chargers).

General CT settings

1- By default, it is set to 3 seconds. However, there may be cases where the user needs to increase this value. For instance, if there are significant distances between the chargers and the ct clamps or if there are numerous interconnected chargers.

  1. Measuring device: The meter should be selected. For UK chargers, it is possible to choose CT clamps
  2. Energy meter address: This information can be found in the meter settings accessed through the meter display.
  3. If the address cannot be located, it is recommended to consult the smart meter manual.

Note: Before calibration, CT have to be connected to the port, but not clamped around the cable.

How to calibrate CT:

1- Before calibration, CT have to be connected to the port, but not clamped around the cable.

2- Check DLB CT and press Calibrate.

3 - Success.