Dynamic load balancing FAQ: Difference between revisions
Appearance
No edit summary |
mNo edit summary |
||
| (2 intermediate revisions by 2 users not shown) | |||
| Line 9: | Line 9: | ||
|- | |- | ||
|2. | |2. | ||
|Can I use simplified charging sequence with Dynamic load balancing | |Can I use simplified charging sequence with Dynamic load balancing? | ||
|Yes, there is | |Yes, there is an option to use both features together, but there are some limitations which are regulated by the standard (IEC 61851-1 / SAE J1772): | ||
# Maximum charging current is only 10 | # Maximum charging current is only 10 Amperes. | ||
# Possible to use only 1-phase charging. | # Possible to use only 1-phase charging. | ||
|- | |- | ||
|3. | |3. | ||
|Can I use 3-phase smart meter for single phase charger? | |Can I use 3-phase smart meter for single phase charger? | ||
|Yes, | |Yes, it is possible to use 1-phase charger with 3-phase smart meter. Please refer to the Energy meter instruction sheet to configure it properly. It is required to select single phase meter in the TeltoCharge application settings. | ||
|- | |- | ||
|4. | |4. | ||
|Does Load balancing | |Does Load balancing limit Dynamic load balancing? | ||
|Yes, if dynamic load balancing is enabled and user | |Yes, if dynamic load balancing is enabled and user wants to achieve maximum charging power without any other limitations except form smart energy meter. [https://wiki.teltonika-energy.com/view/Functionalities#Load_balancing Load balancing] should be set to the maximum value. | ||
|- | |- | ||
|5. | |5. | ||
|If "''use preferred phase''" is enabled, can charger automatically change | |If "''use preferred phase''" is enabled, can the charger automatically change phases? | ||
|Yes, If TeltoCharge detects that prioritized phase is loaded and the maximum current it can give is | |Yes, If TeltoCharge detects that the prioritized phase is loaded and the maximum current it can give is 6 or less amperes, the charger will make a check If other phases are loaded less: | ||
* If there is | * If there is another phase which is loaded less, charger will change charging phase. | ||
* If other two phases | * If other two phases are loaded as well, charger will stop the charging process. | ||
|- | |- | ||
|6. | |6. | ||
|How TeltoCharge | |How does TeltoCharge prioritize phases when phase priority is disabled, TeltoCharge is connected to three phases and three phase charging is disabled? | ||
|Charger checks which phase is least loaded and selects that phase as a charging phase. If during charging process any of other two phases load decreases and the maximum available current | |Charger checks which phase is least loaded and selects that phase as a charging phase. If during charging process any of other two phases load decreases and the maximum available current is 5 amperes higher then the charging phase, TeltoCharge will change charging phase to the least loaded. | ||
|} | |} | ||
Latest revision as of 09:59, 7 August 2026
| No. | Question | Answer |
| 1. | How TeltoCharge sets maximum charging power when 3-phase charging is enabled? | TeltoCharge checks which phase is loaded most, measures how much free current is available, and sets that current. |
| 2. | Can I use simplified charging sequence with Dynamic load balancing? | Yes, there is an option to use both features together, but there are some limitations which are regulated by the standard (IEC 61851-1 / SAE J1772):
|
| 3. | Can I use 3-phase smart meter for single phase charger? | Yes, it is possible to use 1-phase charger with 3-phase smart meter. Please refer to the Energy meter instruction sheet to configure it properly. It is required to select single phase meter in the TeltoCharge application settings. |
| 4. | Does Load balancing limit Dynamic load balancing? | Yes, if dynamic load balancing is enabled and user wants to achieve maximum charging power without any other limitations except form smart energy meter. Load balancing should be set to the maximum value. |
| 5. | If "use preferred phase" is enabled, can the charger automatically change phases? | Yes, If TeltoCharge detects that the prioritized phase is loaded and the maximum current it can give is 6 or less amperes, the charger will make a check If other phases are loaded less:
|
| 6. | How does TeltoCharge prioritize phases when phase priority is disabled, TeltoCharge is connected to three phases and three phase charging is disabled? | Charger checks which phase is least loaded and selects that phase as a charging phase. If during charging process any of other two phases load decreases and the maximum available current is 5 amperes higher then the charging phase, TeltoCharge will change charging phase to the least loaded. |